Key Specifications & Terms
- Estimated Cost:
- SYP 757,670,680 (Seven Hundred Fifty-Seven Million, Six Hundred Seventy Thousand, Six Hundred Eighty Syrian Pounds) according to Ref. No.
16806/S/4 dated 11/6/2026.
- Execution Period:
- 700 calendar days (Seven hundred calendar days).
- Bid Bond (Initial Guarantees):
- 2% of the estimated project value.
- Payable via a certified check drawn to the order of the General Housing Establishment, a bank guarantee covering the bid validity period, or a direct bank transfer from the bidder's account to the Establishment's account.
- Performance Bond (Final Guarantees):
- 2% of the total contract value upon award.
- Payable via a certified check, bank guarantee covering the commitment period, or a bank transfer to the Establishment's account.